Government and Defence data centre procurement: what belongs in your RFP?
A provider can send you a long list of certifications and still leave the question unanswered: does the proposed service meet the requirements of this workload? A useful Government or Defence data centre RFP connects each requirement to the facility, people or system it covers, then asks for evidence you can evaluate.
Start with the workload’s classification and your agency’s security requirements. From there, specify the applicable hosting, physical security, personnel and system-assurance evidence. This guide helps you turn that work into a requirements schedule for government data centre colocation. Your security and procurement advisers should confirm which requirements apply and how the service will be authorised.
Specify the assurance your workload actually requires
Several government frameworks provide a defined basis for evaluation, but they do different jobs. A hosting certification, a personnel clearance and a system assessment cannot stand in for one another. Identify the requirement first, then name the evidence that will satisfy it. For the wider infrastructure decision, our five data centre selection questions cover capacity, support and growth alongside assurance.
Hosting Certification Framework and Certified Strategic status
The Hosting Certification Framework sets requirements for certified services hosting relevant government data and systems. Certified Strategic is its highest certification level. Specify the level and service scope your agency requires, then check the certified entity and facilities against the register. A provider logo does not confirm that every service or site is in scope.
Check the certification pathway early if your timeline depends on a future approval. The HCF website currently states that registration for prospective providers and supplementary assessments was paused from 3 November 2025 during reform, with existing certifications not impacted. Confirm the current position before scoring a promise to certify a new service or extend an existing scope.
Physical security zones and the scope of approval
The Protective Security Policy Framework sets government protective security requirements. Ask your security adviser to specify the zone and the certification or accreditation evidence needed for the proposed space, including relevant SCEC requirements. Request the site and room or hall covered, the assessor or certifying authority and the date. MDC’s compliance and certifications overview is a starting point for identifying the supporting evidence to request from us.
Defence Industry Security Program membership
DISP membership requirements depend on the work and contract. Where membership is required, ask for the relevant levels across governance, personnel, physical, and information and cyber security. Membership in one domain or at one level does not establish every capability your tender may require. Use the Defence requirements and your contract scope to determine what the respondent must evidence.
Personnel security clearances
Define the clearance or vetting requirements for the roles that will access your equipment and systems. Ask how the provider verifies current status, monitors changes and controls access, including for subcontractors. Apply the same role-based scrutiny to remote hands personnel. Use an agreed assurance process for clearance evidence; individual personnel records may be sensitive.
Government and defence data centre information security requirements
The building’s physical controls are only part of the service. Identify the systems the provider operates and those your organisation remains responsible for, then specify the assessment evidence needed at each boundary.
IRAP assessment, stated correctly
Ask for an IRAP assessment, where relevant, using the correct terminology. IRAP assessors evaluate security controls; they do not issue system certification or approval on ASD’s behalf. Request the report or appropriate assurance material, assessment date, classification, scope, exclusions and unresolved findings. The assessment informs your risk and authorisation decision rather than replacing it.
Cyber baseline and assessment scope
Name the framework and version your agency or contract requires. Where Essential Eight maturity requirements apply, specify the target and request assessment evidence across the complete package, including scope, date and remaining gaps. ASD also publishes transition guidance for ASD Essentials for enterprise IT; previous maturity ratings do not automatically convert to the newer assessment ratings. Confirm the applicable requirements with your security team, including whether they cover corporate systems, the management environment or both.
Critical infrastructure and sovereignty obligations
Where the SOCI regime applies, ask how the data centre service supports your government organisation’s relevant obligations as well as the provider’s own. Requirements vary by asset class, so avoid a generic ‘SOCI compliant’ checkbox. Separately, establish the ownership chain, support locations and relevant jurisdictions. These sovereignty considerations need to be assessed against the workload and reflected in the service agreement.
What Should a Government and Defence Data Centre RFP Include?
Use these rows as drafting prompts, then tailor them with your security and procurement advisers. Specify the required level or outcome and the evidence you will accept. That makes it easier to distinguish a confirmed capability from a response that still needs clarification.
| Requirement area | What the RFP should require | Evidence to request |
| Hosting certification | Certification level, certified entity name, and the specific facilities in scope | Entry on the Hosting Certification Framework register, verified by the agency |
| Physical security zoning | Required zone and applicable certification/accreditation for each proposed space | Scope, facility or room, certifying authority, assessment date and approval evidence |
| Defence eligibility | Required DISP membership domains and levels for the work or contract | DISP membership evidence broken down by security category |
| Personnel security | Role-specific clearance or vetting requirements for physical and remote hands access | Clearance assurance and access-control process, including issuing-authority details and currency checks |
| System assurance | IRAP assessment scope, date and classification level, described as assessed | The IRAP assessment report, with controls outside scope disclosed |
| Cyber baseline | Applicable cyber framework and version, required outcome and clearly defined system boundary | Dated assessment evidence, method, assessor and unresolved gaps; confirm treatment of any Essential Eight transition |
| Sovereignty | Corporate ownership chain and the jurisdiction of the ultimate parent | Corporate structure diagram plus change of control notification clauses |
| Supply chain | Subcontractors used, their vetting standard, and where each function is performed | Subcontractor register with delivery locations and vetting evidence |
Make the requirements hold up after contract signature
Tie each requirement to the facilities and services in the colocation proposal. Otherwise, a respondent may provide evidence for a different site or a broader corporate environment. Ask the respondent to identify the scope explicitly, including any dependency on future work or approval.
Also specify how evidence stays current. Agree notification requirements for changes to certification, ownership, key subcontractors or support locations. Include the people delivering on-site work and monitoring, and establish what vetting applies. These obligations give the team managing the contract a way to follow up on the commitments evaluated at tender.
Government data centre RFP checklist
For each applicable item, state the required outcome and an acceptable form of evidence. Mark genuinely inapplicable items with a reason rather than asking every respondent to claim every credential.
• Hosting Certification Framework level, certified entity name and facilities in scope
• Independent verification of that status against the framework register
• Required physical security zone and certification/accreditation scope, authority and date for the proposed space
• Applicable DISP membership domains and levels where required by the work or contract
• Required clearance or vetting levels for relevant roles, with issuing-authority details and an agreed verification process
• Whether on-site and remote hands staff are directly employed or subcontracted
• IRAP assessment report, scope, date and assessed classification level
• Disclosure of any security controls outside the IRAP assessment scope
• Applicable cyber baseline and version, required target, assessment evidence and unresolved gaps
• Whether cyber assurance covers corporate systems, the management environment or both
• Corporate ownership chain and the jurisdiction of the ultimate parent
• Support for the SOCI obligations applicable to your organisation and asset
• Subcontractor register, vetting standard, and the location of each delivered function
• Notification obligations for changes to certification, ownership or control
• Relevant ISO certificates and SOC reports, with entity, service and facility scope and appropriate dates
• The contracted service level, its outage definition, exclusions and remedy
A good requirements schedule lets your team trace each acceptance decision back to evidence. Resolve scope gaps before award, and carry the continuing obligations into the contract. That gives the people running the service a clear basis for checking that it remains suitable.
Looking for a data centre partner that can support your infrastructure today and as your requirements evolve? Macquarie Data Centres provides secure, resilient and scalable data centre solutions for hyperscale, enterprise, government and cloud environments.
Contact us to discuss your requirements, learn more about our team, or request a tour to see our facilities firsthand.
Frequently asked questions
What is Certified Strategic hosting?
Certified Strategic is the highest certification level under the Hosting Certification Framework. Verify the entity and certified service scope against the register. It does not, by itself, authorise your system or establish that every facility offered by the provider is covered.
Can a data centre be IRAP certified?
IRAP is an assessment program, not a system certification. Require the relevant report or assurance material, its scope, date and findings. The assessment helps your organisation understand controls and gaps; your authorisation responsibilities remain.
What SCEC zone does a government data centre need?
The required zone depends on the information, assets and activities involved and the agency’s security assessment. Have your security adviser specify it, together with the required certification or accreditation evidence. Check the proposed room or hall rather than assuming the same approval covers the entire provider portfolio.
Does the Hosting Certification Framework pause affect current tenders?
It may affect a plan that relies on new certification or supplementary assessment. The HCF website currently records a pause from 3 November 2025 during reform, while existing certifications are not impacted. Confirm the status and proposed scope before relying on a future approval in the evaluation.
What is the difference between DISP and a security clearance?
DISP membership applies to an organisation and has levels across several security domains. A personnel security clearance applies to an individual. Determine which organisational membership and role-specific clearances the work requires, then request evidence for each separately.
Should sovereignty requirements be in the RFP or the contract?
Both. Put the evidence requirements in the RFP so ownership structure, parent jurisdiction and support chain locations are assessed at evaluation. Then put continuing obligations in the contract, including notification of any change of control and of any change to certification status, because ownership and certification can both change during a multi-year term.